Referring SCT request for confirmation of LPG & NGL Loadout system by email below, I checked and compare last the punch & defect list,
Item 1: It will be made by SCT & Vendor
Item 2: It will be made by SCT & Vendor ( UAC support final the format )
Item 3: It will be made by SCT & Vendor
Item 4: New cause for add the density data to NGL & LPG Display. ( I’m not such for SCT recommend )