As we have to hand over area level 12, level 14, level 15 and level 16 to hotel interior contractor for prepare and proceed interior work as reference 1. That you have informed us that Façade Outstanding work at level 12 have obstacle can’t work for interior work because the building doesn’t protect the water as reference 2.
We acknowledge regarding façade outstanding work at level 12 as you informed. Currently, we follow up and accelerant to PPS and PISA to protect the damage that will effect with interior work. However, if Façade Outstanding work that doesn’t affect with interior and toilet work, can start to work on 24th October 2015 and please inform to hotel interior contractor to start working on the date as above. If have any damage with interior work in that day from the protection work, we will coordinate with responsible