The Contractor shall furnish all construction plant, utilities, temporary facilities, temporary access road, equipment, materials and supplies required for prosecution of the work but which will not be incorporated in the completed work, unless otherwise specified herein.
Prior to installation of any Contractor-furnished temporary facilities on the jobsite, proposals for such facilities shall be submitted to and written approval received from EGAT.
All temporary structures and facilities furnished by the Contractor shall remain the property of the Contractor and shall be maintained throughout the work. Any materials, equipment, or temporary structures installed or erected on the jobsite or within permanent buildings by the Contractor shall be removed by him when so directed by EGAT to permit the execution of other work in connection with the project or at the completion of the Contractor's work.
All Contractor-furnished construction plant and facilities shall be in first-class condition and shall be of the proper type and size to perform the work. The plant and facilities shall be regularly and systematically maintained throughout the work to ensure proper, efficient and safe operation. Plant and facilities which are inadequate, unsafe or improperly maintained shall be promptly modified, repaired or removed from the site and replaced as directed by EGAT and at the Contractor's expense. EGAT reserves the right to perform regularly inspection of the construction plant and facilities.
When the work is completed, all Contractor-furnished temporary structures and facilities shall be removed from the site and the area shall be restored to its original condition to the maximum extent practicable.
Temporary structures for offices, change houses, warehouses and other uses for the Contractor or his subcontractors shall be provided by the Contractor. Suitable construction trailers may be used in lieu of temporary structures. Such structures or trailers shall be placed only in the locations assigned by EGAT.