Risk Assessment
Delivery & Lifting
Fin will be deliver in pallet of 25piece of 4.4m length. & panels will be delivery in 4.4m length
in individual panel with temporary ‘shoes’ to be removed prior to installation;
Onsite mobile crane supply by customer will assist in installation during the whole of
installation period;
Due to the panel and fin weight, manual lifting will not be considered.
Installation
The installation risk involved mainly due to above ground installation. Magnetic clamps will be
used to provide higher accuracy in positioning and thus reduce the chances of the removal of
spot welding when realignment is needed.
Personal safety is of utmost concern and personal safety check must be done each and everytime
prior to work in high location. All safety related equipment must be check on a weekly
basis to examine if replacement is needed. Any damage to safety equipment must be
immediately dealt with. Additional safety equipment should always be available for immediate
replacement when needed.
Tools and portable equipment must have safety attachment whenever it is in use;
Safety platform should be available to provide added safety.
Wiring of any electrical tools must conform to site requirement and is both sound and
functional.
Fire extinguisher must accompany each welding station. Any other safety requirement demand
by customer or site safety officer must be follow;
END