Mr. M. Frick asked Markus Kapaun and me to evaluate if we can not close
MARS earlier (5th working day); for total MAHLE.
As in the past one major bottle neck was HR we started to review the process
with HR first of all. After some rounds we now got the feedback that most of the HR
departments could provide to us the necessary data by the 2nd working day.
In addition if we will close MARS on the 5th workign day and that we need
the HR data and IC invoices earlier do you see any major road blocks
- within a specific ME
- or a process
which could restrict us to close MARS at the 5th working day?