Pls also provide the following:
• Pls also provide key milestone project implementation lead-time as well as which period that other equipment e.g. air-con room and temperature monitoring system can start along.
• Contracted maintenance cost per year including spare part cost from year 1 to year 10
• Urgent service cost/times and lead-time to provide service
• Calculation design with assumptions
• Refrigerating unit capacity in BTU/Hr
• Total number of refrigerating units
• Total number of spare refrigerating units
• Electricity cost in kWatts-Hr (Units) per Day. Pls specify the number of refrigerating units running for this calculation.
• Pls provide site references.