Please send to me a complete set of approved shopdrawings in scanned copy and let me know the approved date if possible.
Why is there another shopdrawing C1-51 (rev1) dated 22 Mar with your comments & stamp dated 26th Mar that concurred to drawing C1-51 dated 15th Mar? Now MCS is trying to charge extra cost to follow your comments which had already been captured in drawing C1-51 dated 15th Mar.
[Chedi’s comments on dwg C1-51 rev1 dated 22nd Mar] = [MCS dwg C1-51 dated 15th Mar which has been approved]. Thus Chedi’s comments concurred to C1-51 dated 15th March which is the correct one. No changes are initiated.
The percentage of additional cost consist in Lot 1 is minimal and can be secure under your invoice to the L/C. In principle, we have no adverse comments to the modification works quotation but will reply officially in early next week.