Hi Tsering,
WIP board : 17 November 2015. (See picture below).
Active report : Update on dropBox already.(Draft_2015-Nov-17)
Daily brief : Start to assembly RA15017 18 yellow, 5250 pieces today.
Finished good : RA15016 (14W) finished -> Good-4,812, Bad-300
Shipments : We will prepare shipments on 19 Nov 2015 for
- RA15016 Good-system 4,812 pieces
- Finish-system with rust 9 pieces
- Center parts (Lot#250315E1T) 12,128 pieces
Other : 17 Nov 2015 (Tomorrow) I not in the office.
Attach files: 1) Finished_RA15016(JN15019).PDF
2) SUM_RA15016(JN15019).PDF
3) BKK_RA_Planning_2015-Nov-17.PDF
Thank you,
Tiger.