other than as a result of a cause listed in Sub Clause 8.4 (Extension of Time for Completion), then the Owner may instruct the Supplier to submit, under Sub Clause 8.3 (Program), a revised Program and supporting report describing the revised methods which the Supplier proposes to adopt in order to expedite progress and complete within the Time for Completion.