Now we got a very big problem with CNEE! Origin schedule VSL sailing on 16/05 after delay to 18/05 but final will be on 21/05
CNEE is very very upset due to they badly need this machine for produce new product which they promise to deliver to their client. All raw materials are ready but awaiting for machine. The continuous delay of VSL going to cause client’s CNEE cancel order and CNEE asking us for reimburse of their LOSS!
Pls ask delay letter from SITC (Explain cause of delay) and send to us urgently.
Pls let me know duty import.