4. Consideration of Time-cost Trade-offs
From the shopping centre example, it is seen that the PERT/CPM can answer questions such as the total project completion time, the critical activities, and the slack times of the non-critical activities. This, obviously, will give the project manager a clear picture for his control over the project. The project schedule is based on the given cost and finish time of the individual activities.