Please, be informed and see attached internal audit plan 2016
This year our internal audit will be a bit difference than last time about QP document control auditing.
QP document control will handle and audit by the new team of our DCC and clerks who just get the training today.
The other remaining QPs will audit by the main auditors on the plan as usual.
For better work flow together and maintain audit on the schedule, this year 1 auditor will go to audit only 1 time (1 section) .
For flexibility, the schedule is listed by date and within the concerned week in case you are not available on concerned date.
Please, help to inform the auditors in your section who does not have email address about this audit plan.
All QP and standard checklists will provide for all auditors at network location Drive O:/Q.C./Internal Audit 2016.
Audit checklist need to send to QMR (K. Michael) 2 days in advance before the audit for approval before conduct the audit.
Please, conduct the audit according our plan, then we will finish our internal audit on time before surveillance audit from SGS.