- Receive job master plan creation from NISSAN Japan
- After that we set plan master schedule New Model L42L (TEANA) which we have summary all event is ET-Lot ,PT-Lot ,SOP-Lot
- Start Production release BOM data by use read time release Design note around 2 months whole KD part and Local part.
- Set Limit calculation, MDC, Part List by CATS system for issue order to supplier internal and external
- We need issue order was the unique part only.
- Follow up supplier whether can support order keep Due date MRD or not?
- Confirm Tooling and Process for supplier whether can OFF TOOL OFF PROCESS or not?
- After from we release order in system G2B finish already. We will must recheck BOM data again.
- Set meeting confirm about Design change list with designer the make clear whether this is d/note the later and supplier know already. And other about design change each event.
- Set W/I code each part correct according VA department need.
- Present NPES and PPCM before trial vehicle to top management know about readiness of part will trial.