It's very good that you have plan to change S/p by checking its lifetime
I notify you that it could not use budget of planned outage because as email below ; Khun Thanee (TCO) requested our Procurement team (Khun Jurairat) to check budget of planned outage.
However, we have many stores of S/p for reservation of RPCL first lot namely ; Optional S/p ; Strategic S/p and Additional S/p.
If it is not consumable S/p,
RPCL will reimburse us first lot of S/p.
When we use this S/p , we have to replenish it to the store immediately .
Sorry, other budgets of CRESCO will be for corrective maintenance or replenishment of the above S/p.
We are service company, not the owner of power plant.
If you require the said S/p ; you could request EGAT to issue MR. for RPCL approval.
Then, CRESCO will procure and request reimbursement from RPCL accordingly.
Best regards