Dear Both
Since Potonggang is running behind schedule-foundation, footings and basement, should be finished by end of June but they have only do the excavation. The preaparation for other footing have not begin yet. So I want Potonggang to do the following:
1. make Time Recovery PLan to get back on Main Schedule
2. If the Architectural & Structural Plan have column then there should be Column in The Elevation drawing.
this work should be done by our draftman-whom should be on site since the begining of May by being delay in issuing
DPRK's VISA. These and other question they have been asking should be done by these people.
As I have stressed earlier that Potonggang have not present to us the Trial Mixed result yet so I don't think that they can proceed without it since this is the critical point of the Project to progress. The delay is fully on them where they can work on other footing which are not effect by the retaining wall demolition but they opt not to do it and selay in presenting us with the result of the trail mixed concrete.
So please stressed these point on Potonggang.
Hoped to see you both soon
Regards
Thavatchai Rajanivat
BPAC