Company elevators were inspected as required by the legal on 28 November 2013. Load safety of the elevator was not included; however, it has been included in the plan which will be carried out in this month November 2014.
- Main board of company electrical system was located on the 4th floor. Electrical safety inspection of overall system including transformers and earth resistance, the latest inspection was carried out in the last week before the stage 2 audit; however, the latest record showing during the audit was done on 29 November 2013. Deficiencies which found by the electrician was recorded in the report and followed up its improvement e.g. emergency light in the area of electrical main board room on the 4th floor was done.
- Compressors and pressure vessels which used 134A refrigerant were inspected by the mechanical engineer third party on 28 November 2013.
- Building safety inspection was done once a year as required by the legal.
- Fire water pipeline (6” diameter) has been planned to re-install including fire hose cabinets around the site which should be complete within the year 2014 as the safety action plan.
- Emergency lights and fire exits in some area should be increased completely by the end of the year 2014 such as survey room, generator room, and corridor of the generator 2 and in front of the loading area door no. 5 and 6.