Lastly the internal rate of return (IRR) was also employed
in the study. The internal rate of return is the discount rate
that makes the NPV of the project or investment equals zero
(Boardman, 2006). The decision rule is to accept independent
projects with IRR ≥ the opportunity cost of capital or the discount
rate (Gittinger, 1996)