Hello Sir,
Sorry for not to update with post KPI. We worked on many cells and improvement also there. It is time taking for us to update with old workout. But we worked on many cells last week. Most of the activities not completed due to Frequency planning pending from EDOS team and SDCCH increase CR approval pending from customer. We expect this activity will be completed by tomorrow night.
Still we did many neighbor optimization also for worst cells. I will send pre/post KPI for that tomorrow.