Key Objectives:
1. Ensure customer requirements are met
2. Ensure minimum capacity utilization (efficiency) of 75% is achieved wherever possible.
3. Ensure materials are available to begin production on time to plan.
4. Production Plan to be completed 0.5 days after receiving customer order (CO).
5. Issue MO at least 10 days before Production Cut date.
6. Issue production plan every Saturday.
Duties and Responsibilities:
1. Plan production through assign production lines to meet ex-factory dates as required by customer.
2. Update ERP. production and planning modules in accordance with new production plan for above lines.
3. Check with Purchasing Department as to material availability and substitute materials where necessary, if possible.
4. Finding suitable substitute materials where require.
5. Re-check material availability ten days (10) before production is due to start for all Manufacturing Orders (MO).
6. Confirm production finish date with Order Entry.