Dear Khun Sakhamon,
As recently confirmed with our Project team,
Company would like to postpone the activity on 23-Nov-15 due to BV-Project (BEU Area) has urgently shutdown.
Furthermore ,they concerned that our activities (B1 Area) may effected the performance of existing plant due to Company has no manpower to support and take care the activity in this period.
Therefore, Company will inform their available schedule as soon as possible when their plant performance get the recovery.
Sorry for your inconvenience.