Dear Khun Pannipa
Please confirmation for this matter below. And please prepare material when
Compost SV go to GUT site for solve this problem.
We are sending herewith the copy of Punch Item List for Block 1 & Common
Commissioning as received from our GUT site as attached below.
Moreover, the detail of each item is shown as per the following:
1) Isolation pad inside Panel
Owner requested to install acrylic cover for all connecting portion of MCB.
Therefore, we request Compost to install acrylic cover for top of MCB based
on
Owner request. Refer attached photo.
2) Tag No. Sticker for Meter
Compost is requested to install name plate for voltmeter and ammeter
based
on Owner request.
Thank you for your cooperation and hope to you reply and confirm to us.
Request date SV go to GUT site 25 June 2015 .
Best Regards