Cost and Payback Analysis:
The project was funded with $84 million of state money, and the balance from donations raised by the University. Multiple bid alternates were carried throughout the procurement and early construction phases to maintain the flexibility to integrate desired features until the necessary funds could be identified. Bid alternates had to be carefully monitored against the construction schedule to ensure that when they were exercised it did not interfere with construction.