Thank you so much for attending the meeting this morning.
Please let me send all of you our conclusion :-
1.We are going to move the machine on 27th September 2015 start from 08.00am-17.00pm.
2.CNC room will stop cutting on 26th September for let our technician arrange the machine ready to move.
Open the wall and let contractor who move air condition to come for arranging
3.After move we still need 4 days (28th Sept - 1st Oct) for setting the machine , install air compressor system , air vacuum and re install air condition.
CNC production can run again on 2nd October.
4.The meeting today we just aimed to know the day for moving machine first anyway we still need to talk about other details such as moving the leather , cut piece etc.
That we can talk later step by step.
5.I'm sending you the time line as file attached below :-