Supply. The intake must be designed to keep trash and sand out of the supply since these can plug up the ram. If the water is not naturally free of these materials, the intake should be screened or a settling basin provided. When the source is remote from the ram site, the supplyline can be designed to conduct the water to a drive pipe as shown in Figure2. The supply line, if needed, should be at least one pipe diameter larger than the drive pipe.