As per meeting with Ophir energy today, In detail of meeting;
1. Khun Tim Samek CP & L Supervisor (Construction Team)
- This project will rental 1-2 months for installation.
- Expect for consider on Jan’15 because Technip would like to finish installation in June’2016 and Ophir would like to finish installation in March’2016
- Installation schedule, I will ark Khun Collin Luis (Project manager) within next week because he will come to business Trip Ophir Thailand next week.
2. Khun Srestha Chaturabul Production Manager (Operation Team)
- Firstly this project incline to purchase but currently change to rental.
- This year holding project and they consider to use supply boat and FSO stead LQ because they worry about firefighting of LQ not certifiers on Bualaung A but wait confirm after internal meeting again.
- They will finish internal meeting and summarize go ahead in this project on 25 Oct’2015