(a) an extension of time for any such delay, if completion is or will be delayed,
under Sub-Clause 8.4 [Extension of Time for Completion], and
(b) payment of any such Cost plus profit, which shall be included in the Contract Price.
After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause
3.5 [Determinations] to agree or determine (i) whether and (if so) to what extent the
error could not reasonably have been discovered, and (ii) the matters described in
sub-paragraphs (a) and (b) above related to this extent.
(a) an extension of time for any such delay, if completion is or will be delayed,under Sub-Clause 8.4 [Extension of Time for Completion], and(b) payment of any such Cost plus profit, which shall be included in the Contract Price.After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause3.5 [Determinations] to agree or determine (i) whether and (if so) to what extent theerror could not reasonably have been discovered, and (ii) the matters described insub-paragraphs (a) and (b) above related to this extent.
การแปล กรุณารอสักครู่..