but drawing was not received, then again we discussed with supplier & negotiate with him & extend it up to 1st June but again drawing failure. Now we are on 13th June & as I got information from Yoshida san that by next week beginning you will share the Tool Go drawing may be by approx. 17th-18th June.
So on the basis of that if I consider to give Tool go ahead to supplier by 20th June (20th June b'coz supplier required at least 3-4 days for final feasibility check) then development plan will be like as showing below.