Stick the auxiliary earth spikes P and C into the ground deeply.
They should be aligned at an interval of 5-10 m from the earthed equipment under test.
Connect the green lead wire to the earthed equipment under test, the yellow wire to the auxiliary earth spikes P and the red wire to the auxiliary earth spike C from terminals E. P and C of the instrument in order