According to MEA transmission line System, SSUT cannot connected with
MEA transmission line at Kortaw and Prakasa as proposed to ERC.
MEA has studied the new route line for SSUT to be connected with MEA
transmission line system started from Sukhumvit road to the Power Plant
in Bangpoo. The new route line above was confirmed by MEA, TOT, IEAT
and GUSGO and now is on the drawing process