Gunkul has substation subcontractor awarded to Transec Power Services Co., Ltd., collection system subcontractor to MPC SYSTEM Co.,Ltd. Both subcontractors have been mobilized to site. Transec has site set up fenses, and planned to start piling work on 22nd October. MPC has set up site containers and started ductbank on road MR1, Mr2, MR3, that planned to be finished by the end of October.