After I have checked sure for the materials transportation from Rayong to job site NTM-A successfully. I can summarize the schedule working plan as per in the attach file.
From the plan is that the cause of the delay comes from the internal heating coil inside the tank, which now has not carried out an additional 2 course and we have not received the PO. from PAE now.
Please expedite action the PO. to us as soon as possible to ensure continuity of work.