optimistic time estimate
1. minimum time in which the task could be completed
2. everything has to go right
most likely task duration
1. task duration under “normal” working conditions
2. most frequent task duration based on past experience
pessimistic time estimate
1. time required under particularly “bad” circumstances
2. most difficult to estimate, includes unexpected delays
3. should be exceeded no more than 1% of the time