Dear Both
After seeing the second weekly report, its seemed that the Retaining Wall is so thick and ver difficult to break, assume that they don't have concrete breaker which can attached to backhoe.
There are serveral things that from our kick off meeting with Potonggang not progress at all as in your agenda 1 item 3 - this item have been promise to K.Sombut by 15th of May 2016 but nothing coming. Pleased hurry them again, it should have been in our hand two week ago.
the other matter Mr.Sombut asked for were
1. Master Schedule
2. Master Materials Schedule
3. All Materials used in Construction to be Approved
You need to remind them of the Concrete Trial Mixed - if the time come to cast concrete and concrete mixture have not been approved there would be no concreting at all. Delay will on Potonggang themself.
When you visit concrete plant please send me some picture, if permitted.
Re-bar are on site - they can test on those on site please ask Mr.Jo to process.
Most of the questions are of future use, the matter at present are Trials Mixed-Testing of Steel Bar. Method Statement for deep excavation and footing have been submit to you for approval yet.
I will try to hurry Mr. Jukkrit on Architectural problem, Mr.Prasarn on Structural Work
I will try to answer most of your question off hand - if not I will refer to the right person