the Relay F512 will be moved down about 88mm, it will not be in the same level of the relays which are in its neighbour panels.
This problem can't be avoid in some substations such as RTR(3 lines), because it has too many lamps for LTO/CTO,
I discussed this with Khun Rajasak, He and I thought it's not a big problem.
But we need committee to confirm which one you prefer in BPP , and it is OK or not for RTR that we have to move down the Relay F512?