The scope of this report is to analyse the following technical aspects:
(1) Towing condition and ballast plan.
(2) Evaluation of the sea-fastening and barge local strength for WPS14 Jacket
barge by using the stress ratios / unity check results of the sea-fastening and
barge local strength check for WPS12 Jacket barge with consideration of CoG
and the weight of WPS 14 and WPS 12 Jacket.
(3) Check of sea-fastening for WPS7 Riser, WPS7 Riser Protector and tie-in
spools and line pipes.
(4) Bollard pull capacity check of the nominated towing tug “Maritime Raja”