Please help update project status fill in to Column “update status 13 Aug, 2015” referent on column “Respond by” and reply to me on tomorrow for prepare our plant before next step. I think that to “I am project coordinator with K.Por this better for commutation our system krab” from now I hear that to K.Sint set Target 1 Dec, 2015, can be summary as below.
1.) Installed crusher machine for charge paratone 8900E in to the tank Target: 15 Sep 2015
2.) Pilot blending 3 batch before trial batch blend Target: 20 Sep 2015
3.) Trial batch blending 5 batch with CL-Singapore (K.Chin) Target: 20 Sep 2015
4.) Send sample to test about 2 month 20 Nov 2015
5.) Plan to cut of date beetwen 8900D ---> 8900E
Best Regards,