Hi Khun Theerachai,
Drawing we are preparing already. Will submit by next week.
Material I m still waiting for supplier reply will be able to feed back in 2 or 3days time. If supplier got no stock material will delay for 1 month to be supply into Thailand.
Whereas for installtion there will be no problem. If material have I am able to complete the mock up roughly in 1 month time. As carcass installation will take 1 week, soild top need 2 week fabrication and installation for 3 days.
Thanks