Special day sheet
Special day sheet enables the users to programe one or few certain plans of a certain day or in a certain week. As can been seen from the software, user can notice that the 19 lines of the default number in the sheet representing holidays of a whole year. For example, the 1st data in the 1st line refers to Jan 1st –the New Year’s Day. If the date today is Jan 1st, the controller will run the 0 primary programe.
Take line 18th as another example. The meaning of the data in line 18th is if today is Sunday, the controller will run Primary Plan “0”.
When the controller runs to the dates or weeks which are not listed in the sheet, the controller will defiantly run Primary Plan 1. For example, today is Feb 1st (neither today is Sat nor Sunday). Feb 1st is not listed in the sheet; in this case, the controller will run Primary Plan 1.
There are totally 44 special days in the sheet. Here below are the introduction of how to programe these special days.
Users can choose either Date or Week to programe. If the users input both date and week, the system will recognize week only. Under this circumstance, only week will be the valid data. Date will be invalid.
①Input date
Double click the “Date (M/D) with the left-key of the mouse. User will be able to see an interface of the date-sheet bouncing up, as Fig 2-2 shows. User can choose the date that s/he needs from this sheet by pressing the left-key of the mouse. Single click
on both sides, users will be able to change the month. The data of year is in-valid here.
Special day sheetSpecial day sheet enables the users to programe one or few certain plans of a certain day or in a certain week. As can been seen from the software, user can notice that the 19 lines of the default number in the sheet representing holidays of a whole year. For example, the 1st data in the 1st line refers to Jan 1st –the New Year’s Day. If the date today is Jan 1st, the controller will run the 0 primary programe.Take line 18th as another example. The meaning of the data in line 18th is if today is Sunday, the controller will run Primary Plan “0”.When the controller runs to the dates or weeks which are not listed in the sheet, the controller will defiantly run Primary Plan 1. For example, today is Feb 1st (neither today is Sat nor Sunday). Feb 1st is not listed in the sheet; in this case, the controller will run Primary Plan 1. There are totally 44 special days in the sheet. Here below are the introduction of how to programe these special days. Users can choose either Date or Week to programe. If the users input both date and week, the system will recognize week only. Under this circumstance, only week will be the valid data. Date will be invalid. ①Input dateDouble click the “Date (M/D) with the left-key of the mouse. User will be able to see an interface of the date-sheet bouncing up, as Fig 2-2 shows. User can choose the date that s/he needs from this sheet by pressing the left-key of the mouse. Single click on both sides, users will be able to change the month. The data of year is in-valid here.
การแปล กรุณารอสักครู่..