If “the Contractor” is not able to do so due to “the contractor’s “fault, “the Contractor” agrees to be fined by “WCH” 0.01% of the total project cost per day- capped at 10%- until “the Contractor” finishes the works and hand over is completed, in accordance with this agreement.