Pongpan;
Clarifying to your request.
1. Report for inspectors structure (See attached);
- We understood that this is the report of a rectifications related to the comments given in an attached e-mail for a Project updates, 01-Sep-2015. Item# 05 Others.
- If yes, it is initially acceptable. However, I’ll go to check on site on FRI, 18-Sep-2015.
2. GA Drawing VALEO. (See attached);
- We understood that this is As-built of crane structure installation with final alignment.
- If yes, this must be signed for PREPARED by KONE’s supervisor, CHECKED / APPROVED by KONE’s Engineer with endorsement and professional license number.
- We (Tebodin) will review before giving to client for project Handover / Record.
3. Report for Liquid Penetrant Test (Recently given);
- It was signed for inspection by SK NDT & Inspection.
- It still have to be signed for REVIEWED & APPROVED by KONE.
- After that, we (Tebodin) will review before giving to client for project Handover / Record.
4. Drawing Overhead and Structure runway (Recently given);
- This was signed by KONE’s Engineer with copy of a professional license.
- However, it must be incorporated with the above GA Drawing VALEO.
I’m going to the site on FRI, 18-Sep-2015 / 09:30 am. Just still waiting for client confirmation for my visit.
We can discuss about this.