As PISA informed that cannot coordinate with the light contractor for installation façade work at Hotel entrance as reference. PPS have coordinated with CRC and LS acknowledge that the light work is ongoing to provide the contractor and include in the scope of work in Hotel Entrance work as SI no. SI/PISA-050/14 Subject: To Provide and Installation the light Type XL.11 at Hotel Entrance & Hotel Drop off area.
Therefore, we are request to PISA to accelerant to install work in your responsibility that not effect with lighting work that might be work after. Pleased kindly to install from the backpae side for maintenance as we informed before. If you have any conclusion regarding lighting contractor, we will inform you for coordinate.