3. Pre-Commissioning
Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Frequently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this reason the plant should be separated into easily manageable system package, each system package will be Pre-Commissioned as a whole and isolations at the boundaries of the system package will be maintained until the completion of Pre-Commissioning activities. Pre-Commissioning activities include: checking for design conformity, checking the status of electrical, mechanical and instrument installations, running-in of equipment, flushing and cleaning activities, drying etc.
3.1 Mechanical Completion Check & Interim Handover
Immediately prior to the hydro test of each system, a Punch-List will be performed by an integrated Punch- List team consisting of construction, and EPC Commissioning
Engineers (from relevant disciplines). When all “A” type items have been cleared and a small but manageable amount of “B” type items are left, a handover can be progressed from the construction to the commissioning group. Since mechanical completion has been achieved with agreed exception items, it is classed as an interim handover to permit construction completion and Pre-Commissioning activities simultaneously. Control and responsibility of work on the system rest with the commissioning group. Any construction work will require written permission from the Lead-commissioning Engineer of the particular Process Unit. Permission will be granted on a job by job basis. This would involve a line-by-line detailed check of the actual physical installation against the latest P&I diagrams issue, job specifications, piping hanger and support drawings, vendor drawing, etc., for erection of the unit in accordance with all drawings and applicable specification. The systems would also be checked from an operating viewpoint for proper location and orientation of valves, vents, drains, steam tracing and traps, sample connections, etc. Punch lists of deviations,
Installation errors, missing items, etc., shall be prepared and given to the appropriate construction department for correction or completion. Also included in this inspection and check-out would be:
• Vessel Internals - This would include going through each tower and vessel to check the installation of trays, baffles, demisters, spargers, etc., and verifying that the dimensions of all weirs, downcomers, distributors, thermowells, etc., are within specification and are properly oriented, as well assuring the internal cleanliness of each vessel prior to final closure.
• Non-operating Adjustments - All non-operating adjustments, packing of pumps and valves and cold alignment of equipment performed by the construction subcontractors should be spot checked, witnessed or periodically inspected to ensure proper records are being kept and recorded for turnover.
• Piping - Check lists would be prepared on each hydrostatic test system before the system is released for hydrostatic testing. Completion of this punch lists by the construction contractor would be required before the test system is released for testing. Post-hydro punch lists would be prepared and followed through on to ensure that the systems were fully completed and ready for pre-commissioning.
• Electrical Installation - Each electrical circuit and motor installation and their electrical polarity check and insulation resistance measurement would be demonstrated by electrical subcontractor to the Commissioning Subcontractor Team.
• Instrument Installation - Review of instrument installation of correctness according to the instrument drawings and specification. The Commissioning Subcontractor Team would witness and/or approve all instrument calibration and check out procedures or work performed by instrument subcontractor.
• System Pressure Testing - Although the construction contractor is responsible for the actual pressure testing of each system prior to mechanical completion, the Commissioning Subcontractor Team would review the test program and the methods used to ensure satisfactory tightens.
3.2 Pre-Commissioning Period
The site phase of the project will commence at approximately 60% construction completion and activities will be mainly centred on:
• Progression of all of the procedures developed during the Home office phase of the project
• Co-ordinating system turnover and completion
• Monitoring and reporting progress
• Co-ordinating resources, including sub-contract and vendor support
• Liaising with licensors
Main activities developed during Pre-Commissioning phase are:
Punch-Listing
Punch-Listing will be undertaken on a systems basis. An integrated team will be formed to participate in Punch-Listing. An initial Punch-List will be undertaken immediately prior to system handover for Pre-Commissioning purpose. This will probably occur at around the hydro test time. Punch-List items generated at this stage will be incorporated into the Project master Punch-List system. A final Punch-List will be undertaken by system immediately prior to the commencement of commissioning activities. This will be a less stringent
Punch-List and aimed at checking the system over before introducing hydrocarbons
Utilisation of the Pre-Commissioning check sheets will assist in completing a full range of required checks. Punch-Listing progress will be recorded on an A3 set of P&IDs.
System Cleaning
This would include directing the cleaning of systems either by flushing, blowing or chemical cleaning by issuing directives for the necessary temporary connections, utilities and proper line up of the system to be cleaned. When the services of a chemical cleaning subcontractor are required, the Commissioning Team will monitor his performance to ensure a satisfactory cleaning job. Before each system is closed for operating, the lines and equipment would be inspected for cleanliness. Cleaning progress will be recorded on an A3 set of P&IDs.
Equipment Run-In
This would include planning and co-ordinating Vendor representatives for the running in of the equipment and obtaining the necessary utilities to accomplish the run-in for equipment such as blowers, pumps, compressor, motors, turbines, and other machinery or mechanical equipment without process fluids before start-up.
Vessel Loading
This phase would ensure that all catalysts, packing, resins and desiccant loading is performed in a proper manner and accurate records and samples of each material loaded are retained. When all the activities foreseen in the Pre-Commissioning phase (the Process
Units will be ready to receive hydrocarbons, most of the utility systems will be live to the respective units and all of the hydrocarbon lines will be positively isolated at the unit battery limits) have been performed successfully a Ready for Commissioning Certificate will be issued and so Commissioning activities can start.
0/5000
จาก: -
เป็น: -
ผลลัพธ์ (ไทย) 1: [สำเนา]
คัดลอก!
3. ก่อนทดสอบการเดินระบบ
ก่อนทดสอบการเดินระบบกิจกรรมเริ่มต้นเมื่อได้รับความสมบูรณ์กลโรงงาน หรือระบบ การ บ่อยอย่างไรก็ตาม ก่อนทดสอบการเดินระบบกิจกรรมซ้อนกลเสร็จกิจกรรม และด้วยเหตุนี้โรงงานควรแบ่งออกเป็นแพคเกจระบบสามารถจัดการได้ง่าย แพคเกจแต่ละระบบจะมีล่วงหน้ามอบหมายอำนาจหน้าที่ทั้งหมด และจะรักษา isolations ในขอบเขตของระบบจนเสร็จสมบูรณ์ก่อนทดสอบการเดินระบบของกิจกรรม กิจกรรมก่อน Commissioning รวม: ตรวจสอบการออกแบบให้สอดคล้อง การตรวจสอบสถานะของเครื่องจักรกล ไฟฟ้าและติดตั้งเครื่องมือ ทำงานในเครื่อง ลบ และทำความสะอาดกิจกรรม ฯลฯ อบแห้ง
3.1 ตรวจสอบเสร็จสมบูรณ์กล&ถึงการส่งมอบระหว่างกาล
ทันทีก่อนทดสอบน้ำของแต่ละระบบ รายเจาะจะดำเนินการ โดยทีมงานรายการเจาะใบรวมประกอบด้วยงานก่อสร้าง และทดสอบการเดินระบบ EPC
วิศวกร (จากสาขาวิชาที่เกี่ยวข้อง) เมื่อสินค้าชนิด "A" ทั้งหมดได้ถูกล้าง และมี ขนาดเล็ก แต่จัดการจำนวนสินค้าประเภท "B" เป็นซ้าย ถึงการส่งมอบสามารถจะหน้าไปเพียงใดจากการก่อสร้างการ commissioning เนื่องจากได้รับความสมบูรณ์กลกับรายการข้อยกเว้นเห็น มันเป็น classed เป็นถึงการส่งมอบการชั่วคราวเพื่ออนุญาตการก่อสร้างเสร็จและก่อนทดสอบการเดินระบบกิจกรรมพร้อมกัน ควบคุมและรับผิดชอบงานระบบพักผ่อนกับกลุ่ม commissioning งานก่อสร้างใด ๆ จะต้องมีลายลักษณ์อักษรจากวิศวกรทดสอบการเดินระบบเป้าหมายของหน่วยประมวลผลเฉพาะ จะได้รับสิทธิ์ในงานโดยงาน นี้จะเกี่ยวข้องกับ--บรรทัดตรวจสอบรายละเอียดการติดตั้งจริงจริงกับ P&I ล่าสุดไดอะแกรมปัญหา รายละเอียดงาน ภาพวาดแขวนและสนับสนุนท่อ ผู้วาด ฯลฯ ., การก่อสร้างของหน่วยทั้งหมดวาดและข้อกำหนดที่เกี่ยวข้อง ระบบจะยังสามารถตรวจสอบจากจุดปฏิบัติงานในตำแหน่งเหมาะสมและการวางแนวของวาล์ว ช่อง ท่อระบายน้ำ ไอน้ำติดตาม และดัก เชื่อมต่อตัวอย่าง ฯลฯ รายการของความแตกต่าง ชก
ข้อผิดพลาดการติดตั้ง การขาดสินค้า ฯลฯ ., จะเตรียมพร้อม และให้แผนกก่อสร้างที่เหมาะสมสำหรับการแก้ไขหรือดำเนินการ รวมอยู่ในนี้ตรวจสอบ และเช็คจะ:
•เรือ Internals - นี้จะรวมไปถึงทาวเวอร์และเรือเพื่อตรวจสอบการติดตั้งถาด พุ่ง demisters, spargers ฯลฯ แต่ละ และตรวจสอบที่มิติของทั้งหมด weirs, downcomers จำหน่าย thermowells ฯลฯภายในข้อกำหนด และแนวได้อย่างถูกต้อง เช่นมั่นใจความสะอาดภายในของเรือแต่ละก่อนปิดท้ายด้วย
•ปฏิบัติไม่ใช่ปรับปรุง - ปรับปรุงการปฏิบัติไม่ใช่ทั้งหมด บันทึกของปั๊ม และวาล์วและเย็นจัดตำแหน่งของอุปกรณ์ที่ดำเนินการ โดยผู้รับเหมาก่อสร้างควรจุดตรวจสอบ เห็น หรือตรวจสอบเป็นระยะ ๆ เพื่อให้แน่ใจว่าระเบียนที่เหมาะสมจะถูกเก็บ และบันทึกไว้สำหรับหมุนเวียน
•ท่อ - ตรวจสอบรายการจะจัดเตรียมระบบการทดสอบแต่ละระบบจะออกใช้สำหรับการทดสอบที่หยุดนิ่ง เสร็จสิ้นการเจาะนี้แสดง โดยการก่อสร้างผู้รับเหมาจะต้องก่อนปล่อยระบบทดสอบสำหรับการทดสอบ รายการเจาะหลังน้ำจะเตรียม และตามทางในเพื่อให้แน่ใจว่า ระบบได้เสร็จสมบูรณ์ และพร้อมสำหรับล่วงหน้าทดสอบการเดินระบบ
•ติดตั้งไฟฟ้า - แต่ละวงจรไฟฟ้า และติดตั้งมอเตอร์และของขั้วไฟฟ้าตรวจและฉนวนกันความร้อนความต้านทานวัดที่จะแสดงให้เห็นว่า โดยเหมาไฟฟ้าทีมเหมาทดสอบการเดินระบบ
•ติดตั้งเครื่องมือ - ตรวจสอบการติดตั้งเครื่องมือของความถูกต้องตามภาพวาดเครื่องมือและข้อมูลจำเพาะ ทีมเหมาทดสอบการเดินระบบจะเป็นพยาน หรืออนุมัติการปรับเทียบเครื่องมือทั้งหมด และตรวจสอบขั้นตอนหรืองานที่ทำ โดยมือเหมา
•ระบบความดันทดสอบ - แม้ว่าผู้รับเหมาก่อสร้างรับผิดชอบสำหรับการทดสอบความดันที่เกิดขึ้นจริงของแต่ละระบบก่อนที่จะเสร็จสมบูรณ์กล ทีมเหมาทดสอบการเดินระบบจะตรวจสอบโปรแกรมทดสอบ และวิธีการใช้ให้พอกระชับหน้าของ.
3.2 ระยะ Pre-Commissioning
ระยะไซต์ของโครงการจะเริ่มที่ประมาณ 60% ก่อสร้างเสร็จ และกิจกรรมจะเป็นส่วนใหญ่ศูนย์กลางบน:
•ความก้าวหน้าของขั้นตอนการพัฒนาระยะของโครงการสำนักงานบ้าน
• Co-ordinating ระบบหมุนเวียนและเสร็จสมบูรณ์
•ตรวจสอบและรายงานความคืบหน้า
• Co-ordinating ทรัพยากร รวมถึงการสนับสนุนสัญญาย่อยและผู้จัดจำหน่าย
• Liaising กับผู้
กิจกรรมหลักที่พัฒนาในช่วงก่อนทดสอบการเดินระบบของเฟส:
เจาะรายการ
เจาะรายการจะดำเนินการตามระบบ มีทีมงานรวมจะเป็นรูปแบบการมีส่วนร่วมในรายการเจาะ จะให้ดำเนินการเจาะรายการการเริ่มต้นทันทีก่อนถึงการส่งมอบระบบสำหรับก่อนทดสอบการเดินระบบของวัตถุประสงค์ นี้อาจจะเกิดที่รอบเวลาทดสอบไฮโดร รายการเจาะตลาดที่สร้างขึ้นในขั้นตอนนี้จะรวมอยู่ในโครงการหลักรายการเจาะระบบ จะให้ดำเนินการเจาะรายการสุดท้าย โดยระบบทันทีก่อนเริ่มดำเนินกิจกรรม commissioning นี้จะเข้มข้นน้อย
เจาะรายการตรวจสอบระบบผ่านก่อนแนะนำไฮโดรคาร์บอน
อิเล็กทรอนิคส์ของแผ่นงานก่อน Commissioning เครื่องจะช่วยดำเนินการตรวจสอบจำเป็นมากมาย รายการเจาะกำลังจะถูกบันทึกเป็นชุด A3 ของ P&IDs
ระบบทำความสะอาด
นี้จะรวมถึงผู้กำกับทำความสะอาดระบบ โดยลบ เป่า หรือทำความสะอาดเคมี โดยออกคำสั่งสำหรับการเชื่อมต่อชั่วคราวจำเป็น สาธารณูปโภคและบรรทัดเหมาะสมค่าของระบบการทำความสะอาด เมื่อบริการผลิตเคมีทำความสะอาดที่จำเป็น ทีมทดสอบการเดินระบบจะตรวจสอบประสิทธิภาพการทำงานของเขาให้งานทำความสะอาดเป็นที่พอใจ ก่อนปิดระบบแต่ละระบบการปฏิบัติการ บรรทัดและอุปกรณ์จะสามารถตรวจสอบสำหรับความสะอาด ความคืบหน้าการทำความสะอาดจะถูกบันทึกเป็นชุด A3 ของ P&IDs
Run-In อุปกรณ์
นี้จะรวมถึงการวางแผนและ co-ordinating ผู้จัดจำหน่ายผู้แทนสำหรับใช้ในอุปกรณ์และสาธารณูปโภคที่จำเป็นได้รับสำเร็จ run-in สำหรับอุปกรณ์เช่น blowers ปั๊ม คอมเพรสเซอร์ มอเตอร์ กังหัน และอื่น ๆ เครื่องจักรกล โดยของเหลวกระบวนการก่อนที่จะเริ่มต้น up.
โหลดเรือ
เฟสนี้จะให้แน่ใจว่าทุกสิ่งที่ส่งเสริม บรรจุภัณฑ์ เรซิ่นและการโหลดชื้นจะดำเนินการในลักษณะเหมาะสมและระเบียนที่ถูกต้อง และมีสะสมของวัสดุแต่ละโหลด เมื่อกิจกรรมทั้งหมดที่ foreseen ในระยะก่อน Commissioning (การ
หน่วยจะพร้อมที่จะรับสารไฮโดรคาร์บอน ส่วนใหญ่ระบบยูทิลิตี้จะอยู่หน่วยเกี่ยวข้อง และบรรทัดไฮโดรคาร์บอนทั้งหมดจะแยกบวกที่จำกัดแบตเตอรี่หน่วย) ได้ดำเนินการเสร็จเรียบร้อยพร้อมจะออกใบรับรองการทดสอบการเดินระบบ และเพื่อ ทดสอบการเดินระบบของกิจกรรมสามารถเริ่มต้น
การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 2:[สำเนา]
คัดลอก!
3. Pre-Commissioning
Pre-Commissioning activities start when the plant, or system, achieves Mechanical Completion. Frequently however, Pre-Commissioning activities overlap Mechanical Completion activities and for this reason the plant should be separated into easily manageable system package, each system package will be Pre-Commissioned as a whole and isolations at the boundaries of the system package will be maintained until the completion of Pre-Commissioning activities. Pre-Commissioning activities include: checking for design conformity, checking the status of electrical, mechanical and instrument installations, running-in of equipment, flushing and cleaning activities, drying etc.
3.1 Mechanical Completion Check & Interim Handover
Immediately prior to the hydro test of each system, a Punch-List will be performed by an integrated Punch- List team consisting of construction, and EPC Commissioning
Engineers (from relevant disciplines). When all “A” type items have been cleared and a small but manageable amount of “B” type items are left, a handover can be progressed from the construction to the commissioning group. Since mechanical completion has been achieved with agreed exception items, it is classed as an interim handover to permit construction completion and Pre-Commissioning activities simultaneously. Control and responsibility of work on the system rest with the commissioning group. Any construction work will require written permission from the Lead-commissioning Engineer of the particular Process Unit. Permission will be granted on a job by job basis. This would involve a line-by-line detailed check of the actual physical installation against the latest P&I diagrams issue, job specifications, piping hanger and support drawings, vendor drawing, etc., for erection of the unit in accordance with all drawings and applicable specification. The systems would also be checked from an operating viewpoint for proper location and orientation of valves, vents, drains, steam tracing and traps, sample connections, etc. Punch lists of deviations,
Installation errors, missing items, etc., shall be prepared and given to the appropriate construction department for correction or completion. Also included in this inspection and check-out would be:
• Vessel Internals - This would include going through each tower and vessel to check the installation of trays, baffles, demisters, spargers, etc., and verifying that the dimensions of all weirs, downcomers, distributors, thermowells, etc., are within specification and are properly oriented, as well assuring the internal cleanliness of each vessel prior to final closure.
• Non-operating Adjustments - All non-operating adjustments, packing of pumps and valves and cold alignment of equipment performed by the construction subcontractors should be spot checked, witnessed or periodically inspected to ensure proper records are being kept and recorded for turnover.
• Piping - Check lists would be prepared on each hydrostatic test system before the system is released for hydrostatic testing. Completion of this punch lists by the construction contractor would be required before the test system is released for testing. Post-hydro punch lists would be prepared and followed through on to ensure that the systems were fully completed and ready for pre-commissioning.
• Electrical Installation - Each electrical circuit and motor installation and their electrical polarity check and insulation resistance measurement would be demonstrated by electrical subcontractor to the Commissioning Subcontractor Team.
• Instrument Installation - Review of instrument installation of correctness according to the instrument drawings and specification. The Commissioning Subcontractor Team would witness and/or approve all instrument calibration and check out procedures or work performed by instrument subcontractor.
• System Pressure Testing - Although the construction contractor is responsible for the actual pressure testing of each system prior to mechanical completion, the Commissioning Subcontractor Team would review the test program and the methods used to ensure satisfactory tightens.
3.2 Pre-Commissioning Period
The site phase of the project will commence at approximately 60% construction completion and activities will be mainly centred on:
• Progression of all of the procedures developed during the Home office phase of the project
• Co-ordinating system turnover and completion
• Monitoring and reporting progress
• Co-ordinating resources, including sub-contract and vendor support
• Liaising with licensors
Main activities developed during Pre-Commissioning phase are:
Punch-Listing
Punch-Listing will be undertaken on a systems basis. An integrated team will be formed to participate in Punch-Listing. An initial Punch-List will be undertaken immediately prior to system handover for Pre-Commissioning purpose. This will probably occur at around the hydro test time. Punch-List items generated at this stage will be incorporated into the Project master Punch-List system. A final Punch-List will be undertaken by system immediately prior to the commencement of commissioning activities. This will be a less stringent
Punch-List and aimed at checking the system over before introducing hydrocarbons
Utilisation of the Pre-Commissioning check sheets will assist in completing a full range of required checks. Punch-Listing progress will be recorded on an A3 set of P&IDs.
System Cleaning
This would include directing the cleaning of systems either by flushing, blowing or chemical cleaning by issuing directives for the necessary temporary connections, utilities and proper line up of the system to be cleaned. When the services of a chemical cleaning subcontractor are required, the Commissioning Team will monitor his performance to ensure a satisfactory cleaning job. Before each system is closed for operating, the lines and equipment would be inspected for cleanliness. Cleaning progress will be recorded on an A3 set of P&IDs.
Equipment Run-In
This would include planning and co-ordinating Vendor representatives for the running in of the equipment and obtaining the necessary utilities to accomplish the run-in for equipment such as blowers, pumps, compressor, motors, turbines, and other machinery or mechanical equipment without process fluids before start-up.
Vessel Loading
This phase would ensure that all catalysts, packing, resins and desiccant loading is performed in a proper manner and accurate records and samples of each material loaded are retained. When all the activities foreseen in the Pre-Commissioning phase (the Process
Units will be ready to receive hydrocarbons, most of the utility systems will be live to the respective units and all of the hydrocarbon lines will be positively isolated at the unit battery limits) have been performed successfully a Ready for Commissioning Certificate will be issued and so Commissioning activities can start.
การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 3:[สำเนา]
คัดลอก!
3 . ก่อนการว่าจ้าง
ก่อนว่าจ้างกิจกรรมเริ่มเมื่อพืช หรือใช้ระบบเครื่องกล , เสร็จ บ่อย อย่างไรก็ตาม ก่อนการว่าจ้างกิจกรรมซ้อนกิจกรรมจบเครื่องกลและสำหรับเหตุผลนี้พืชที่ควรจะแยกออกเป็นแพคเกจของระบบที่จัดการง่ายแต่ละระบบจะได้รับแพ็คเกจก่อนรับหน้าที่เป็นทั้งและ isolations ที่ขอบเขตของระบบจะถูกเก็บรักษาไว้จนกว่าจะเสร็จก่อนการจัดกิจกรรม ก่อนการว่าจ้างกิจกรรมต่างๆรวมถึง : การตรวจสอบการออกแบบที่สอดคล้องกัน การตรวจสอบสถานะของไฟฟ้า ติดตั้งเครื่องจักรกล และอุปกรณ์ ใช้ในอุปกรณ์ล้างและทำความสะอาด กิจกรรมการอบแห้งฯลฯ
3.1 กลเสร็จตรวจสอบ&ระหว่างแฮนด์
ทันทีก่อนที่จะทดสอบพลังของแต่ละระบบ รายการเจาะจะดำเนินการโดยบูรณาการ Punch - รายชื่อทีม ประกอบด้วย การก่อสร้างและการว่าจ้างวิศวกร ( EPC
จากสาขาวิชาที่เกี่ยวข้อง ) เมื่อทั้งหมด " " รายการประเภทได้รับการล้าง และเป็นจำนวนเงินที่เล็ก ๆแต่ง่ายต่อการจัดการของ " บี " รายการประเภทอยู่ด้านซ้ายเป็นระบบที่สามารถสร้างขึ้นจากการว่าจ้างของกลุ่ม ตั้งแต่จบเครื่องกลได้รับความกับตกลงรายการข้อยกเว้น มันเป็น classed เป็นระบบชั่วคราวให้เสร็จก่อนการว่าจ้างก่อสร้างและกิจกรรมพร้อมกัน ควบคุมและรับผิดชอบงานในส่วนระบบ มีการว่าจ้างกลุ่มงานก่อสร้างใด ๆ จะต้องได้รับอนุญาตเป็นลายลักษณ์อักษรจากตะกั่วการว่าจ้างวิศวกรของหน่วยกระบวนการที่เฉพาะเจาะจง ได้รับอนุญาตจะได้รับในงาน โดยงานพื้นฐาน บรรทัดนี้จะเกี่ยวข้องกับการตรวจสอบรายละเอียดของการติดตั้งทางกายภาพที่แท้จริงกับล่าสุด P &ผมภาพปัญหา ประเภทงานท่อ , ไม้แขวนรูปวาดและภาพวาด , สนับสนุน , ผู้ขาย ฯลฯสำหรับการก่อสร้างของหน่วยตามแบบและข้อกำหนดที่เกี่ยวข้อง ระบบจะถูกตรวจสอบจากมุมมองสำหรับตำแหน่งที่เหมาะสม และการดำเนินงานของวาล์วระบาย ระบายไอน้ำ , ติดตามและกับดักตัวอย่างการเชื่อมต่อ ฯลฯ ชกรายการเบี่ยงเบน
ติดตั้งข้อผิดพลาด รายการที่ขาดหายไป เป็นต้นจะได้เตรียมให้หน่วยงานก่อสร้างที่เหมาะสมเพื่อแก้ไข หรือ ความสมบูรณ์ นอกจากนี้ในการตรวจสอบนี้และแบบด่วนจะ :
- เรือ internals - นี้จะรวมไปถึงแต่ละหอ และเรือ เพื่อตรวจสอบการติดตั้งแผ่นกั้น demisters spargers , ถาด , ฯลฯ และการตรวจสอบว่าขนาดของฝาย , downcomers ผู้จัดจำหน่าย thermowells ฯลฯอยู่ภายในกำหนดและจะถูกวางเป็นอย่างดี มั่นใจความสะอาดภายในแต่ละเรือก่อนที่จะปิดสุดท้าย
- ไม่ผ่าตัดปรับ - ไม่ปรับทุกงานบรรจุของปั๊มและวาล์ว และอุปกรณ์จัดเย็นโดยการก่อสร้างผู้รับเหมาควรมีจุดตรวจเห็นหรือการตรวจสอบเป็นระยะเพื่อให้แน่ใจว่าระเบียนที่เหมาะสมจะถูกเก็บและบันทึกไว้สำหรับการหมุนเวียน .
- ท่อ - รายการตรวจสอบจะเตรียมในแต่ละทดสอบ hydrostatic ระบบ ก่อนที่ระบบจะออกทดสอบ hydrostatic . ความสมบูรณ์ของรายการชกโดยผู้รับเหมาก่อสร้างจะต้องก่อนการทดสอบระบบจะเปิดให้ทดสอบไฮโดรโพสต์รายการชกจะเตรียม และตามเพื่อให้แน่ใจว่าระบบสมบูรณ์และพร้อมก่อนการว่าจ้าง .
- ติดตั้งระบบไฟฟ้า - ไฟฟ้าและมอเตอร์แต่ละวงจรการติดตั้งและตรวจสอบขั้วไฟฟ้าและการวัดความต้านทานของฉนวนจะถูกแสดง โดยการว่าจ้างผู้รับเหมาไฟฟ้าผู้รับเหมาช่วงเพื่อทีม
- การติดตั้ง - ตรวจสอบเครื่องมืออุปกรณ์การติดตั้งถูกต้องตามแบบรูปและสเปค การว่าจ้างผู้รับเหมา ทีมที่จะเป็นพยานและ / หรืออนุมัติทั้งหมดเครื่องมือสอบเทียบและตรวจสอบกระบวนการหรือการปฏิบัติงาน โดยผู้รับเหมา
เครื่องดนตรีระบบแรงดัน - ทดสอบ - แม้ว่า งานก่อสร้าง รับผิดชอบจริงความดันทดสอบของแต่ละระบบก่อนการว่าจ้างผู้รับเหมา กลไกสมบูรณ์ ทีมงานจะตรวจสอบทดสอบโปรแกรมและวิธีการที่ใช้เพื่อให้เป็นที่พอใจก่อน

3.2 กระชับ ระยะเวลาการว่าจ้างเว็บไซต์ในโครงการต่างๆ จะเริ่มที่ประมาณ 60% ก่อสร้างเสร็จ และจะเป็นศูนย์กลางหลักใน :
- ความก้าวหน้าของขั้นตอนการพัฒนาในขั้นตอนของโครงการโฮมออฟฟิศ -
Co กฎหมายการหมุนเวียน และตรวจสอบระบบการรายงานความก้าวหน้าและความสมบูรณ์ -

- Co กฎหมายทรัพยากร รวมถึงสัญญาย่อยและผู้ขาย สนับสนุน
- ติดต่อประสานงานกับผู้ออกใบอนุญาต
กิจกรรมหลักพัฒนาช่วงระยะก่อนการชกรายการรายการ :

เจาะจะดำเนินการบนพื้นฐานของระบบ ทีมรวมจะเกิดขึ้นที่จะเข้าร่วมในรายการเจาะ มีรายการชกครั้งแรกจะมีปัญหาทันทีก่อนที่จะมีระบบก่อนมีการว่าจ้าง นี้อาจจะเกิดขึ้นรอบ ๆน้ำ ทดสอบเวลาชกในรายการที่สร้างขึ้นในขั้นตอนนี้จะถูกรวมเข้าไปในโครงการปริญญาโท ชกรายการระบบ รายการชกครั้งสุดท้ายจะดำเนินการโดยระบบทันทีก่อนที่จะเริ่มต้นของการว่าจ้างต่างๆ นี้จะมีรายการชกอย่างเข้มงวด
น้อยลง และมุ่งตรวจสอบระบบก่อนแนะนำไฮโดรคาร์บอน
ความสำคัญของการตรวจสอบแผ่นก่อนจะช่วยในการเต็มรูปแบบของความต้องการการตรวจสอบ ความคืบหน้ารายการเจาะจะถูกบันทึกไว้บน A3 ชุด P &รหัส ระบบทำความสะอาด

นี้จะรวมถึงการทำความสะอาดของระบบให้ โดยการล้าง , เป่าหรือสารเคมีทำความสะอาดออกสั่งให้จําชั่วคราวเชื่อมต่อสาธารณูปโภคและบรรทัดที่เหมาะสมของระบบการทำความสะอาด เมื่อการบริการของเคมีทำความสะอาดผู้รับเหมาจะต้องทำการ ทีมงานจะตรวจสอบประสิทธิภาพของเขาเพื่อให้แน่ใจว่า งานทำความสะอาดที่น่าพอใจ ก่อนที่แต่ละระบบ ปิด เพื่อปฏิบัติการ สายและอุปกรณ์จะถูกตรวจสอบเพื่อความสะอาด ซักแห้งความคืบหน้าจะถูกบันทึกไว้บน A3 ชุด P &

อุปกรณ์ใช้ในรหัสนี้จะรวมถึงการวางแผนและบริษัทกฎหมายตัวแทนผู้ขายสำหรับใช้ในอุปกรณ์และการสาธารณูปโภคที่จำเป็นเพื่อให้บรรลุวิ่งในอุปกรณ์ เช่น เป่า , ปั๊ม , ปั๊มลม , มอเตอร์ , กังหันลม , และเครื่องจักรอื่น ๆหรืออุปกรณ์เครื่องกลไม่มีของเหลวกระบวนการก่อนที่จะเริ่ม
เรือโหลด
เฟสนี้จะตรวจสอบให้แน่ใจว่าทุกตัวเร่งปฏิกิริยาบรรจุเม็ดสารดูดความชื้นโหลด และจะดำเนินการในลักษณะที่เหมาะสมและการบันทึกที่ถูกต้องและตัวอย่างของวัสดุแต่ละโหลดยังคง เมื่อกิจกรรมทั้งหมดล่วงหน้าก่อนการว่าจ้างในเฟส ( กระบวนการ
หน่วยจะต้องพร้อมที่จะรับสารไฮโดรคาร์บอนที่สุดของโปรแกรม ระบบ จะอยู่ตามหน่วยและทั้งหมดของไฮโดรคาร์บอนสายจะมีทางแยกที่หน่วยแบตเตอรี่จำกัด ) ได้รับการว่าจ้างให้เรียบร้อยแล้วพร้อมใบรับรองจะออกและการมอบหมายกิจกรรมจะเริ่ม
การแปล กรุณารอสักครู่..
 
ภาษาอื่น ๆ
การสนับสนุนเครื่องมือแปลภาษา: กรีก, กันนาดา, กาลิเชียน, คลิงออน, คอร์สิกา, คาซัค, คาตาลัน, คินยารวันดา, คีร์กิซ, คุชราต, จอร์เจีย, จีน, จีนดั้งเดิม, ชวา, ชิเชวา, ซามัว, ซีบัวโน, ซุนดา, ซูลู, ญี่ปุ่น, ดัตช์, ตรวจหาภาษา, ตุรกี, ทมิฬ, ทาจิก, ทาทาร์, นอร์เวย์, บอสเนีย, บัลแกเรีย, บาสก์, ปัญจาป, ฝรั่งเศส, พาชตู, ฟริเชียน, ฟินแลนด์, ฟิลิปปินส์, ภาษาอินโดนีเซี, มองโกเลีย, มัลทีส, มาซีโดเนีย, มาราฐี, มาลากาซี, มาลายาลัม, มาเลย์, ม้ง, ยิดดิช, ยูเครน, รัสเซีย, ละติน, ลักเซมเบิร์ก, ลัตเวีย, ลาว, ลิทัวเนีย, สวาฮิลี, สวีเดน, สิงหล, สินธี, สเปน, สโลวัก, สโลวีเนีย, อังกฤษ, อัมฮาริก, อาร์เซอร์ไบจัน, อาร์เมเนีย, อาหรับ, อิกโบ, อิตาลี, อุยกูร์, อุสเบกิสถาน, อูรดู, ฮังการี, ฮัวซา, ฮาวาย, ฮินดี, ฮีบรู, เกลิกสกอต, เกาหลี, เขมร, เคิร์ด, เช็ก, เซอร์เบียน, เซโซโท, เดนมาร์ก, เตลูกู, เติร์กเมน, เนปาล, เบงกอล, เบลารุส, เปอร์เซีย, เมารี, เมียนมา (พม่า), เยอรมัน, เวลส์, เวียดนาม, เอสเปอแรนโต, เอสโทเนีย, เฮติครีโอล, แอฟริกา, แอลเบเนีย, โคซา, โครเอเชีย, โชนา, โซมาลี, โปรตุเกส, โปแลนด์, โยรูบา, โรมาเนีย, โอเดีย (โอริยา), ไทย, ไอซ์แลนด์, ไอร์แลนด์, การแปลภาษา.

Copyright ©2024 I Love Translation. All reserved.

E-mail: