According to the weekly meetings on 21 Mar 2014, kindly be confirmed that commencement date of the PSC-G3 set on 24 Mar 2014.
Regarding this matter, you’re requested to submit the following documents below;
- detailed drawings of Access Road, Well Location, Camp site and etc.
- progress of project delivery on a regular basis every week.
- other related i.e. safety information, work procedure
Note – next meeting Friday 28th, we would like to conduct with safety information with our safety team. So, please your prepare for lesson learn from PSC-G1 and share in the meeting i.e. good practice and improvement items plus foreseeable topics at new location (rain, access, community etc.)