The project is estimated to be of average risk, so its WACC is 10%.
(1) What is Project P's NPV? What is its IRR? its MIRR?
(2) Draw Project P's NPV profile. Does Project P have normal or nonnormal cash flows? Should this project be accepted? Explain.