Priority now to pin down the correct complete scope of work as per EDG current direction first.
GW and KPK to re-estimate the cost per standard top level room and run through with owner team.
To this end, suggest that GW takes the last as-built drawings for mockup room and update it for EDG comments – this set of dwgs should reflect the Option D understanding + EDG field report issued 9th Apr (de-conflicted as one exercise) – by this week?
Tim, quite a few items in the room were to be re-designed and simplified, how far along are you on the revised design sketches? Only then can GW draft it into the above-mentioned dwgs.
Khun Phon to note, there are new items (e.g. outdoor balcony screens) inserted by Tim in the field report, dwgs and costing on this basis first for reporting.