2) No further comment from Capt.Rachai regarding schedule integrity, only emphasis schedule very tight and less of buffer time.
For using shore crane instead of ship crane also not recommended and he confident that MOL will not use shore crane as well.
To evaluate service P&L by using shore crane, he only advise higher stevedorage cost by usd15/teu both laden and empty to factor in P&L but Yangon port stay remain unchanged at 120 hrs.
(Base on his comment > we have ever used shore crane in the past but failed because of cargo loss by cut and run) therefore, we decided to use ship crane by then.
He said "don't expected to get more buffer time fm using shore crane as practically will not be happened as past experience while cost were increased.