Bidder to ensure adequate quantity of Key personnel, those proposed onshore and offshore PMT key personnel shall be dedicated to the project.
c.) Bidder submitted manpower plan not in accordance with Bidder installation work schedule.
d.) Bidder to review and confirm on work durations in the Remote platform WP2 and WP3 with no AWB is alongside the wellhead platform, the maximum POB is only 16. Breakdown as follows:
SUBCONTRACTOR/Contractor = 12 POB max.
Due to limited POB Work shall be properly managed by discipline.
Due to limitation of POB in the remote platform CONTRACTOR consider and plan to allocate AWB will be alongside alternately for a period of 2 weeks each of the three (3) platforms (WP2, WP3 and WP1 for ZPQ works). Gangway connection will be performed by SUBCONTRACTOR including preparation of lifting and rigging equipments.
CONTRACTOR provided attached the proposed minimum manpower plan and duration of offshore execution.