Please see below for details as per your question.
1. Possible to start built up partition for store room at B1 as per request area on this Saturday 14 Mar.
2. Project will start on 22 Mar 2015 and 4 months of period time to complete the project.
3. Will complete close the B1 female toilet for pass way to our service elevator # 2 to loading Contractor staff and materials.