Bidder to review allocation of proposed list of construction tools, rigging and lifting equipments and construction equipments for offshore implementation to be segregate in details dedicated tools of each BF platforms requirements. it is noted from the provided list of tools and equipments, i.e only 4 units of welding machines provided, PWHT equipments, no Generators provided and lacking of others major tools and equipments used for typical BF modifications works. Tools of the trade quantities shall be in accordance of the manpower plan or workforce requirement for the Works.
Bidder to ensure ZONE 2 Diesel Engine GENERATOR and AIR COMPRESSOR required and supplied at process area ZPQ.
Semi-ZONE 2 (Rigsafe type) will be utilized in WP2 and WP3.
Bidder upon award of SUBCONTRACT to submit Up-to-date list of Inspection & proof load Certificates for all Rigging and Lifting Equipment, cargo handling equipments (baskets, containers, gas racks) and the maintenance records.
CONTRACTOR provided attached the minimum major equipment and quantity to be utilized offshore SUBCONTRACTOR to provide the overall list as required.