Obligation of the Parties
Article 5: The obligation of Party “ A” to Party “B”
5.1 Party “A”will send all documents and permission of relevant projects agreed by Royal Government for National Road No. 5 Construction.
5.2 Will send capital announcement document for supplying in this National road construction to Party “B” after signing on memorandum for 10 days.
5.3 Facilitate public administration work to Party “B” during construction implementation.
5.4 Party “A” will limit the facility for the construction work site and raw materials such as soil, stone, red gravel, rubber, cement and metal to Party “B”.
5.5 Party “A”will calculate the expenditure to Party “B” on the project.
5.6 Party “A”will give Party “B” .....% of total money .......................... (...................................................................................) US Dollars.
5.7 Party “A” is responsible for Party “B” to import all machineries and materials (like Asphalt) for construction without paying tax on import (100% of tax free).